To cable the node, complete the following steps, using the illustration for reference.
Note
You can only cable a maximum of two disk shelves per loop.
| 1 | Cable the first FC HBA to Bank 1 of Switch 1 and Switch 2. In the example, Port A of the FC HBA is cabled to Port 0 of Switch 1 and Port B is cabled to Port 0 of Switch 2. |
| 2 | Cable the second FC HBA to Port 1 on both switches, with Port A on Switch 1 and Port B on Switch 2. |
| 3 | Connect the Pool 0 disks to Bank 2, Pool 0 of the switches by completing the following steps:
In the example, the Pool 0 disk shelves are connected to Switch Port 8 on both Switch 1 and 2. |
| 4 | Connect the Pool 1 disks to Bank 1, Pool 1 of the switches by completing the following steps:
In the example, the disk shelves are connected to Switch Port 4 on both Switch 1 and 2. |
| 5 | Confirm that the disks are visible and have dual paths by entering the following command on the console: storage show disk -p ResultsThe output shows the disks connected to the switches, to what port they are connected, and to what disk and to which LRC/ESH they belong, as shown in the following example: Exampleha15*> storage show disk -p PRIMARY PORT SECONDARY PORT SHELF BAY ha15sw:2.40 A ha16sw:2.40 B 5 0 |
| 6 | Connect one ISL cable to any port on each switch. In the example, Port 13 is used on both switches. |
| 7 | Connect the VI-MC cluster adapter to the switches, with Port 1 connecting to Switch 1 and Port 2 to Switch 2. |
| 8 | |
| 9 | Check to make sure that the node can see all disk shelves by entering the following command on the console: vol status -r Result |
| 10 | Go to the remote site and follow the instructions in Step 4: Cabling the remote switches and node. |
Copyright © 1994-2003, Network Appliance, Inc. All rights
reserved.
Part No. 210-00580
File: ch3metr5.htm
Last updated: 12/03/03 17:45:14