To cable the node, complete the following steps, using the applicable diagram for reference.
Note
You can only cable a maximum of two disk shelves per loop.
| 1 |
Cable the first Fibre Channel HBA of the local node to Switch 1 and Switch 2. In the example, one port (0a) of the Fibre Channel HBA is cabled to Port 0 of Switch 1 and the second port (0b) is cabled to Port 0 of Switch 2. |
| 2 |
Cable the second Fibre Channel HBA of the local node to Switch 1 and Switch 2. In the example, one port (0c) of the Fibre Channel HBA is cabled to port 1 of Switch 1 and the second port (0d) is cabled to port 1 of Switch 2. |
| 3 |
Connect the local node pool 0 disks to the switches by completing the following substeps:
Note In the example, the pool 0 disk shelves are connected to switch port 9 on both Switch 1 and 2. However, you can use any open set of switch ports in this quadrant (limited to ports 8-11 in this configuration). |
| 4 |
Connect the remote node pool 1 disks to the switches by completing the following substeps:
In the example, the pool 1 disk shelves are connected to switch port 5 on both Switch 1 and 2. However, you can use any open set of switch ports in this quadrant (limited to ports 4-7 in this configuration). |
| 5 |
Confirm that the disks are visible and have dual paths by entering the following command on the console: storage show disk -p ResultsThe output shows the disks connected to the switches, to what port they are connected, and to what disk and to which LRC, ESH, or ESH2 they belong, as shown in the following example: Exampleha15*> storage show disk -p PRIMARY PORT SECONDARY PORT SHELF BAY switch1:4.40 A switch2:4.40 B 5 0 |
| 6 |
Connect one ISL cable to any port on each switch, making sure that the ports have the same number. In the example, Port 13 is used on both switches. |
| 7 |
Connect the VI-MC cluster adapter to the switches, with one port connecting to Switch 1 and the second port to Switch 2. Note |
| 8 | |
| 9 |
Check to make sure that the node can see all disk shelves by entering the following command on the console: aggr status -r Result |
| 10 |
Go to the remote site and follow the instructions in Stage 4: Cabling the switches and nodes at the partner site. |
Copyright © 1994-2005, Network Appliance, Inc. All rights
reserved.
Part No. 210-01386_C0
File: ch3_mci6.htm
Last updated: 21-Dec-2005 11:31:57