Performing a giveback
Types of giveback operations
You can perform the following types of giveback operations from the takeover node:
- Normal giveback
- Giveback and terminate processes
- Forced giveback
Initiating normal giveback
To initiate normal giveback, complete the following step.
Step
|
Action
|
|
1
|
Enter the following command on the command line of the takeover node:
cf giveback
Note If the giveback fails, there might be a process running that prevents giveback. You can wait and repeat the command, or you can follow the steps outlined in Terminating processes to initiate giveback.
After a giveback, the takeover node's ability to take over its partner automatically is not reenabled until the partner reboots successfully. If the partner fails to reboot, you can enter the cf takeover command to initiate a takeover of the partner manually.
|
Terminating processes to initiate giveback
Some storage system processes prevent a giveback from being completed. If this happens, you can either wait for the process to be complete, or you can terminate the process early to initiate a giveback operation.
Processes that can prevent giveback
The cf giveback command does not succeed if any of the following events are taking place on the emulated node at the same time:
- Dump and restore processes
- Outstanding CIFS sessions
- RAID disk additions
- Volume creation (traditional volume or FlexVolTM volume)
- Aggregate creation
- Disk ownership assignment
- Disks being added to a volume (vol add)
- SnapshotTM copy creation, deletion, or renaming
- Quota initialization
- Advanced mode repair operations, such as wafliron
- Storage system panics
- Backup dump and restore operations
- SnapMirror® transfers (if the partner is a SnapMirror destination)
- SnapVaultTM restorations
- Disk sanitization operations
Terminating the process and initiating a giveback
To terminate a process early and initiate giveback to the failed node, complete the following step.
Step
|
Action
|
|
1
|
On the takeover node, enter the following command:
cf giveback -f
Note If you invoke cf giveback -f and it fails, the takeover node panics. After the takeover node recovers, you can attempt the giveback -f command again. If you cannot successfully perform a giveback using the -f option, you must force giveback using the forcegiveback command. See Forcing giveback.
|
Forcing giveback
The takeover node might detect an error condition on the failed node that typically prevents a complete giveback, such as data not being flushed from NVRAM to the failed node's disks.
To force the takeover node to give back the resources of the failed node even if the takeover node detects an error that typically prevents a complete giveback, complete the following step.
Step
|
Action
|
|
1
|
On the takeover node, enter the following command:
cf forcegiveback
Attention Use cf forcegiveback only when you cannot get cf giveback to succeed. When you use this command, you risk losing any data committed to NVRAM but not to disk.
|
What happens when a giveback is interrupted
If the takeover node experiences a failure or a power outage during the giveback process, the giveback process stops and the takeover node returns to takeover mode when the failure is repaired or the power is restored.